The Blue Grass Chemical Agent-Destruction Pilot Plant (BGCAPP) main plant continued systemization, or testing, activities for preparation of operations during August. Technicians began testing components of the supercritical water oxidation system. Interferent testing was conducted in the laboratory, this test is completed with chemicals and materials used at BGCAPP to ensure nothing interferes with the air monitoring equipment. Enhanced On-site Container movement training continued. The Human Health Risk Assessment was completed. This assessment, which is required by the U.S. Environmental Protection Agency, is performed to assess the potential effect a facility like BGCAPP could have on human health and the environment. The Static Detonation Chamber continues to process projectiles, destroying a total of 4.5 U.S. tons as of Aug. 23.