The Blue Grass Chemical Agent-Destruction Pilot Plant (BGCAPP) main plant continued systemization, or testing, activities for preparation of operations including continued Demilitarization Protective Ensemble certification and toxic area entries practice. Testing of the Agent Neutralization Reactor batch sampling and processing took place at BGCAPP. Technicians tested single-round containers with helium during integrity tests. The containers are required to be tested every 90 days to be deemed service-ready. The Static Detonation Chamber continued to process projectiles and in the main plant, a total of 56 of 59 systems have been turned over to the operations team.